Results
| |
|
|
| |
Monumental Archway |
|
Based on the initiative of the Syrian Directorate General of Antiquities and Museums and the DAI Damascus, the monumental archway, situated 1km south-east of Suweida, was restored in Spring 1998 (see images). Experienced local workers carried out the conservation measures according to the results of a survey by the architect G. Stanzl of the Landesamt für Denkmalpflege Rheinland Pfalz. Initially, a concrete ceiling built into the west face of the monument was removed. The walls were repaired using old, roughly hewn basalt ashlars rather than concrete. The general aim of these measures was the conservations of the original building to as high a degree as possible. Furthermore, the general appearance of the monument was not to be disrupted by the inclusion of new and smoothly worked stones.
|